Construction Update No.4 March 2025

1 April 2025

Stage 1 and 2 involving road excavation and construction of underground drainage is now complete. Stage 3 now includes construction of Little Gold Street and the raised shared zone area at the western end of the site, adjacent Jewell Station, while we wait for the specialist contractors required for the service relocation at the eastern end of the street.

The change of staging has allowed us to keep progressing with the project in a timely manner. The eastern stormwater works will be undertaken as soon as possible, meaning there are two possibilities for stage 4 works, either the southern footpath works or the final stormwater stage.

For more information on the latest staging and dates please refer to Construction update flyer No.4 March 2025 and Construction update: Temporary Loading Zones March 2025.