Construction Update 5 - April 2025

1 May 2025

What is happening?

During the past weeks:

  • Stage 4 Service relocation works have been completed.
  • Southern paving works, including the kerb and street furniture is progressing on track.
  • Stage 6 Additional eastern service is currently in progress by specialist contractors.

What is coming up?

  • Our Civil contractor will continue working on Stage 5 and Stage 6 in the next 3-4 weeks.
  • Although Stage 3 is complete, due to safety, this area will still be closed to vehicles until Stage 5 and Stage 7 are completed (to allow through-traffic).
  • Temporary Loading Zone arrangement for Little Gold St & Sydney Rd will be in place between 22 April-16 May 2025 (an additional 1.5 weeks)

For more information on the latest staging and dates please refer to the Construction update flyer no. 5 and the Temporary loading zones - April flyer