News

Construction Project Update No. 8 - July 2025

24 July 2025

Southern footpath works are progressing, with the section from Jewell Station to Black Street mostly complete with furniture and planting outstanding.

Stage 9, the northern footpath works, including the kerb and driveways, has commenced and is due for completion at the end of July.

What is coming up?

Stage 10, the eastern shared zone next to the existing bouldering park will take place next.

Works are on track for a September finish!


For more information on the latest staging and dates please refer to Construction update flyer No.8 July 2025