News

Construction update: remaining play items and new completion date

5 November 2026

Construction of the new playspace is almost complete. We have a few items that have been delayed but will be installed soon.

Order of remaining works

  • Timeline item 1 - incomplete

    Install junior play item

    Mid-February 2026

  • Timeline item 2 - incomplete

    Install concrete footings for the senior play item

    Mid-February 2026

  • Timeline item 3 - incomplete

    Install remaining park fencing

    End February 2026

  • Timeline item 4 - incomplete

    Opening of completed playspace areas

    Expected end February-early March 2026.

    Temporary fencing will keep the senior play item area closed

  • Timeline item 5 - incomplete

    Demolish existing playspace

    Early March 2026

  • Timeline item 6 - incomplete

    Complete install of senior play item

    Expected May 2026

  • Timeline item 7 - incomplete

    Playspace complete

We have chosen to install different items in place of the custom play items as we have not been able to resolve the issues causing the delays. We have chosen pre-made options that are as close to the custom designs as possible. The senior play unit will still be an aeroplane themed unit, like in our original concept.

Remaining items

Click on the spots to see more about the items that we will be installing.

Sewell Reserve final plan

Final concept plan

Sewell Reserve updated final plan

Visit the project page to see more about how we developed the concept design.