News

Construction Project Update No. 2 - 11 March 2022

15 March 2022

What is happening?

During the past weeks:

  • Starlie Geikie, the artist of the artwork conducted a fun paper weaving workshop for the locals in January.
  • Council finally received a permit from the Department of Transport for the start of construction.
  • Business surveys were conducted with the shops by the Economic Development unit to match them with suitable programs.

What is coming?

Over the next fortnight:

  • A storage area will be set up on the rear car parking area of Campbell Turnbull Library. Three carparking spaces will still be available for visitors.
  • Stage 1 will commence on 16 March as shown on the Staging Plan. The works will include demolition, excavation, kerb and channel and footpath works.

View the Staging Plan - 11 March 2022


More information

  • Minor updates to our construction plan will be updated on the main project page.
  • Any significant changes will be hand delivered to affected properties as early as possible.