Project update – February 2021

11 February 2021

Construction is progressing well with the following site activities completed:

  • In ground services installation have been completed
  • Concrete structure is complete onsite
  • Underground water tanks have been installed and the car park is being formed
  • Structural steel framing installation has been completed
  • Timber structure has been installed in Zone 1 & 2 and continues throughout rest of site;
  • Brickwork installation in Zone 1 is ongoing
  • Roof has been installed in Zone 1 with Zone 2 underway