  • The building structure has been completed and enclosed
  • The internal building fit out is underway with furniture being installed
  • Landscaping works to the hub and Bridget Shortell Reserve are ongoing and nearing completion
  • Testing and commissioning of services are in progress
  • Carpark at the hub has been asphalted