Project Update – December 2020

1 December 2020

Construction is progressing well on site with the following activities completed:

  • Installation of the inground rain water tank has been finished;
  • Fit out of the repurposed bike shed for a public toilet and community garden storage shed is continuing;
  • Concrete slab including both the ground floor and the suspended floor has been poured on site
  • Lift shaft and the concrete stairwell has been installed
  • Structural steel installation is 50% complete on site and continuing
  • Structural timber installation has commenced with the Zone 1 building is nearing completion
  • Brickwork installation has commenced in the Zone 1
  • Site will be closed during the holiday period and reopen in mid Jan 2021