Construction is progressing well with the following site activities completed:

  • Fit out to ground floor change rooms is complete
  • Fit out to new umpires change rooms and gym is nearing completion
  • Fit out to the new ground floor DDA facilities, laundry and medical room is ongoing
  • Level 1 make good works are ongoing
  • Level 2 grandstand seating is being installed
  • Level 2 Multipurpose room fit out is nearing completion
  • Lift has been installed and await for commissioning
  • External curtain wall installation has commenced
  • Civil works have commenced
  • Balustrades and handrails are being installed throughout