Project update – April 2021

15 April 2021

Construction is progressing well with the following site activities completed:

  • Timber structure installation and fire rating is continuing
  • Roof is being installed with library roof to complete
  • Brickwork installation is nearing completion
  • Internal partitions commenced and is ongoing in POD 1
  • Services rough in has commenced in POD 1 and is ongoing
  • Windows and glazing are being installed throughout

Important update – Bridget Shortell Reserve

As part of the project, the contractor will commence the park upgrade works on the Bridget Shortell Reserve in June 2021. The reserve will be fenced off and unavailable for public use for the next 6-7 months until the project completion in Jan 2022.

The park upgrade works include new planting, improved pathways, new playground, shaded BBQ area and a public amenity.

Council apologises for any inconvenience this may cause but look forward to delivering an improved park for the local community.