Kent Road Works

28 November 2022

Works to commence in December

We have scheduled the modifications of the separated bicycle lane trials on Kent Road in Pascoe Vale.

We are planning to commence works on Monday 5 December 2022. These works are expected to take 5 working days to complete. Our contracted workers will be present on Sunday 4 December to set up the work zone on the southern side of Kent Road.


What will be happening

During this time, the kerbing separating the bike lanes and the parking lanes will be removed to allow for new line marking to be completed. Following this, the revised separator kerbing will be installed. The works will be staged to ensure minimal disruption to properties along Kent Road. Please find a cross section showing the street layout at the back of this letter.

Kent Road will remain open to vehicle access during this time. However, access to trial bike lanes may be restricted during periods of works. You will be informed via letter drop of any potential further impacts.

Have your say

We want to know how these changes affect you. We will engage with you in the new year to make sure all your opinions are heard and considered.


Thank you for your continued interest in this project.